Specifies the constraint type for a task.
Namespace: Microsoft.Office.Project.Server.Library
Assembly: Microsoft.Office.Project.Server.Library (in Microsoft.Office.Project.Server.Library.dll)
Syntax
'Declaration
Public Enumeration ConstraintType
'Usage
Dim instance As Task.ConstraintType
public enum ConstraintType
Members
| Member name | Description | |
|---|---|---|
| AsSoonAsPossible | Value=0. As soon as possible (ASAP). | |
| AsLateAsPossible | Value=1. As late as possible (ALAP). | |
| MustStartOn | Value=2. Must start on (MSO). | |
| MustFinishOn | Value=3. Must finish on (MFO). | |
| StartNoEarlierThan | Value=4. Start no earlier than (SNET). | |
| StartNoLaterThan | Value=5. Start no later than (SNLT). | |
| FinishNoEarlierThan | Value=6. Finish no earlier than (FNET). | |
| FinishNoLaterThan | Value=7. Finish no later than (FNLT). |
Remarks
Use the Task.ConstraintType type to set the TASK_CONSTRAINT_TYPE property in a ProjectDataSet.TaskRow object.