For a Task, FinishVariance is the amount of time that represents the difference between a task's baseline finish date and its current finish date.
For an Assignment, it is the difference between an assignment's baseline finish date and its scheduled finish date.
<FinishVariance>
  IntegerValue
</FinishVariance>
Parent Elements
Occurrences
| Minimum: 0 Maximum: 1 | 