Enable Defender for SQL Servers on Machines

Important

This article applies to commercial clouds. If you're using Government clouds, see the Enable Defender for SQL servers on Machines government article.

The Defender for SQL Servers on Machines plan is one of the Defender for Databases plans in Microsoft Defender for Cloud. Use Defender for SQL Servers on Machines to protect SQL virtual machines (VM) and Azure Arc SQL Server instances.

Important

The Defender for SQL Servers on Machines plan is undergoing a transition to the new agent architecture. For more information, see Defender for SQL Servers on Machines plan transition.

Prerequisites

Communication: Allow outbound HTTPS traffic on Transmission Control Protocol (TCP) port 443 using Transport Layer Security (TLS) to *.<region>.arcdataservices.com URL. Learn more about URL requirements.

  • Extensions: Ensure these extensions aren't blocked in your environment. Learn more about restricting extensions installation on Windows VMs.

    • Defender for SQL (IaaS and Arc)
      • Publisher: Microsoft.Azure.AzureDefenderForSQL
      • Type: AdvancedThreatProtection.Windows
    • SQL IaaS Extension (IaaS)
      • Publisher: Microsoft.SqlServer.Management
      • Type: SqlIaaSAgent
    • SQL IaaS Extension (Arc)
      • Publisher: Microsoft.AzureData
      • Type: WindowsAgent.SqlServer
  • Supported SQL Server versions - SQL Server 2012 (11.x) and later versions.

  • Supported operating systems- Windows Server 2012 R2 and later versions.

Enable the plan

Enable the plan on an Azure subscription

To enable the Defender for SQL servers on machines plan, you need to enable the Defender for Databases plan on your subscription. The Defender for SQL servers on machines plan is included in the Defender for Databases plan.

  1. Sign in to the Azure portal.

  2. Navigate to Microsoft Defender for Cloud > Environment settings.

  3. Select the relevant subscription.

  4. On the Defender plans page, locate the Databases plan and select Select types.

    Screenshot that shows you where to select types on the Defender plans page.

  5. In the Resource types selection window, toggle the SQL Servers on Machines plan to On.

    Screenshot that shows where to toggle the Defender for SQL servers on machines, to on.

  6. Select Continue > Save.

Enable the plan on an Amazon Web Services (AWS) or Google Cloud Platform (GCP) subscription

To enable the Defender for SQL servers on machines plan, you need to enable the Defender for Databases plan on your subscription. The Defender for SQL servers on machines plan is included in the Defender for Databases plan.

  1. Sign in to the Azure portal.

  2. Search for and select Microsoft Defender for Cloud.

  3. Select Environment settings.

  4. Select the relevant AWS or GCP subscription.

  5. On the Defender plans page, locate the Databases plan and select Settings.

  6. In the SQL Servers on machines section, toggle the SQL Servers on machines plan to On.

    Screenshot that shows where to locate the on button for Defender for SQL Servers on machines is located.

  7. Select Save.

Enable the plan at the SQL Server resource level

We recommend enabling the plan on your entire Azure subscription. However, you might need to enable Defender for SQL on machines on specific machines.

To enable the plan on specific machines, you need to disable the plan on the subscription and apply the following instructions to the relevant machines at the resource level.

  1. In the Azure portal, search for and select:

    • Azure Arc > Data services > SQL Server instances.
      or
    • SQL virtual machines.
  2. Select the relevant SQL Server instance.

  3. Locate the security menu and select Microsoft Defender for Cloud.

    Screenshot that shows where to locate Defender for Cloud under the security section.

  4. Select Enable Microsoft Defender for SQL servers on Machines.

    Screenshot that shows where to enable Defender for SQL servers on machines.

Verify that your machines are protected

Important

Don't skip this step, as it's important to verify your deployment is protected.

Depending on your environment, it can take a few hours to discover and protect SQL instances. As a final step, you should verify that all machines are protected.